The following project is at the end of its sixth week. Find the cost and

schedule variances. Also, find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the ETC and EAC for the project. Comment on the project status.

also using the 50-50 rule for planned value and earned value. Comment on the project status.