Online Learning
CLICK HERE TO ORDER YOUR ASSIGNMENT

A customer requested Change Order was approved and there is a new baseline schedule and budget What does

Question

A customer requested Change Order was approved, and there is a new baseline schedule and budget. What does

this mean? (select all that apply)

A) The project WBS, requirements, scope, schedule and budget must all be updated as well as the Risk and Quality Plans

B) Earned Value measures and variances need to use the new baseline schedule and budget

C) The project has to start again, beginning with the Initiation Phase

D) The Change Control Board will need to review the Change Order

E) The project Stakeholders need to be notified of the new baseline and changes to the Project Plan

Project Management

A customer requested Change Order was approved and there is a new baseline schedule and budget What does